United States βΊ Grid βΊ Interconnection queues βΊ Texas
ONSHORE WIND Β· ERCOTStella 2 Wind
Stella 2 Wind is a 201 MW onshore wind request suspended in the ERCOT interconnection queue, in Kenedy County, Texas.
Queue statusPaused / redesign
- PlanningQueued Jun 2013 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2022 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 16INR0012
- Grid region
- ERCOT (Texas)
- Developer
- Eon
- Connection point (POI)
- tap 345kV 80076 Ajo - 80071 Zorillo
- Location
- Kenedy County, Texas
- Technology
- Wind: 201 MW
- Total requested
- 201 MW
- Study phase
- FIS
- Queue status
- Suspended
- Entered queue
- 12 June 2013
- Proposed online date
- December 2022
Location
Marker shows the centre of Kenedy County; the queue data does not give exact sites.
Other requests in Kenedy County
- Tall Saddle WindOnshore wind Β· 523 MW Β· in study
- Green Ocelot SolarSolar + storage Β· 357 MW Β· in study
- Tall Saddle SolarSolar Β· 252 MW Β· in study
- Green Ocelot StorageSolar + storage Β· 179 MW Β· in study
- Gulf Wind 2Onshore wind Β· 227 MW Β· suspended
- Stella 1 WindOnshore wind Β· 201 MW Β· built
- Gulf Wind 2 ExpansionOnshore wind Β· 47.9 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem