United States β€Ί Grid β€Ί Interconnection queues β€Ί Washington

SOLAR + STORAGE Β· WEST

Solar + storage project TCS-10, Lincoln County

Solar + storage project TCS-10, Lincoln County is a 40.0 MW solar + storage request withdrawn in the West interconnection queue, in Lincoln County, Washington, connecting to Avista Utilities.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2019 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
TCS-10
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Harrington Substation 115kV
Location
Lincoln County, Washington
Technology
Solar: 40.0 MW Β· Battery
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
Request Status: Withdrawn; Facilities Study: N/A; Phase One Cluster Study: N/A; Phase One Re-Study: N/A; Phase Two Clust
Queue status
Withdrawn
Entered queue
10 December 2019
Proposed online date
July 2021
Withdrawn
March 2023

Location

Marker shows the centre of Lincoln County; the queue data does not give exact sites.

Power plants in Washington Β· Transmission lines in Washington

Other requests in Lincoln County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem