Completed queue projects in PJM (Mid-Atlantic, Midwest) — page 21

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,19297.6 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,192 requests · page 21 of 24
ProjectCapacityStatusLocationRegionQueuedOnline
Baler LF
Other
3.8 MWOperating Bergen, NJPJM May 20012003
Warren County Landfill
Solar
3.8 MWOperating Warren, NJPJM Jun 20122014
Beaverbrook (Kinsley Solar)
Solar
3.8 MWOperating Gloucester, NJPJM Apr 20132015
Levittown 13 kV Solar
Solar
3.7 MWOperating Burlington, NJPJM Jul 20162020
Warren County LF
Other
3.6 MWOperating Warren, NJPJM Jan 20052007
Other project H20, Prince George's County
Other
3.5 MWOperating Prince George's, MDPJM Jan 20022003
Roundtop Energy Project
Gas
3.5 MWOperating Susquehanna, PAPJM Aug 20122015
Mill Creek
Solar
3.5 MWOperating Burlington, NJPJM Apr 20112011
Constellation Solar Maryland II, LLC Solar Facility
Solar
3.4 MWOperating Dorchester, MDPJM Apr 20122015
Sussex County Land Fill
Other
3.4 MWOperating Sussex, NJPJM Aug 20092011
Exelon Epuron Solar Energy Center
Solar
3.3 MWOperating Bucks, PAPJM Aug 20072008
Turkey Hill Dairy WF
Onshore wind
3.2 MWOperating Lancaster, PAPJM Oct 20092011
Orchard Hills
Other
3.2 MWOperating Berrien, MIPJM Mar 20112013
Glra LF
Other
3.2 MWOperating Lebanon, PAPJM Jun 20062007
Northwest Ohio Wind
Solar + storage
3.2 MWOperating Paulding, OHPJM Mar 20202021
SECCRA Units 1, 2 & 3
Other
3.2 MWOperating Chester, PAPJM Sep 20092010
Gardy's Mill Solar
Solar
3.2 MWOperating Westmoreland, VAPJM Jan 20182020
I-95 Landfill Phase 2
Other
3.2 MWOperating Fairfax, VAPJM Aug 20102011
Wabash Valley Power Association, Inc.
Other
3.2 MWOperating Jay, INPJM Jan 20132015
Seven Islands Environmental Solutions, LLC
Other
3.2 MWOperating WVPJM Oct 20152017
Carbon Limestone Landfil Gas to Electricity Facility
Other
3.2 MWOperating Mahoning, OHPJM Nov 20102012
Charleston Clean Energy
Other
3.2 MWOperating Kanawha, WVPJM Jan 20132019
Kelford Solar Park
Solar
3.1 MWOperating Bertie, NCPJM Oct 20142015
Shawville Generating Station
Gas
3.0 MWOperating Adams, PAPJM Sep 20192020
Brookside Energy Center
Other
3.0 MWOperating New Castle, DEPJM Jul 20112012
Southern Landfill Units 1-4
Other
3.0 MWOperating New Castle, DEPJM Dec 20042006
Everitt Solar Farm
Solar
3.0 MWOperating Hunterdon, NJPJM Jul 20102016
Millhurst Solar Farm
Solar
3.0 MWOperating Monmouth, NJPJM Feb 20102016
Louisa Gas Turbines Units 1 through 5
Gas
3.0 MWOperating Orange, VAPJM Nov 20082009
Gas project D29, Montgomery County
Gas
3.0 MWOperating Montgomery, MDPJM Jul 20002001
Essex County Correctional Facility
Gas
3.0 MWOperating Essex, NJPJM Sep 20112014
Augusta Solar Farm
Solar
3.0 MWOperating Sussex, NJPJM Jan 20112016
Burlington Generating Station
Gas
3.0 MWOperating Burlington, NJPJM Feb 20132015
Dresden Nuclear Generation Station, Units 2 & 3
Nuclear
3.0 MWOperating Grundy, ILPJM Mar 20112013
Mill Run WF
Onshore wind
3.0 MWOperating Fayette, PAPJM Jul 20032005
GEMS Landfill Solar
Solar
3.0 MWOperating Camden, NJPJM Mar 20162022
Wetteland Solar Farm
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20112016
Stafford Regional LF
Other
3.0 MWOperating Stafford, VAPJM Aug 20072008
Bernards Township Solar Farm
Solar
3.0 MWOperating Somerset, NJPJM Apr 20112016
Frenchtown 2 Solar
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20102012
Harmony Solar Farm
Solar
3.0 MWOperating Warren, NJPJM Apr 20102015
Frenchtown 1 Solar
Solar
3.0 MWOperating Hunterdon, NJPJM Jan 20102011
Owens Corning Solar
Solar
3.0 MWOperating Camden, NJPJM Oct 20112017
Granger Electric of Hancock County
Other
3.0 MWOperating Hancock, OHPJM Nov 20092015
Lumberton SP
Solar
2.9 MWOperating Burlington, NJPJM Nov 20092010
Matrix-Stults Road
Solar
2.9 MWOperating Middlesex, NJPJM Oct 20102011
Legler Landfill Solar Farm
Solar
2.9 MWOperating Ocean, NJPJM Oct 20152021
Solar project W2-071, Burlington County
Solar
2.8 MWOperating Burlington, NJPJM Jul 20102011
Worcester South
Solar
2.6 MWOperating Worcester, MDPJM Apr 20142019
Kettle Run
Solar
2.6 MWOperating Burlington, NJPJM Feb 20182023
Page 21 of 24

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)