🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Ohio

SOLAR + STORAGE · PJM

Northwest Ohio Wind

Northwest Ohio Wind is a 3.2 MW solar + storage request built and operating in the PJM interconnection queue, in Paulding County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Mar 2020 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-103
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Haviland 138 kV
Location
Paulding County, Ohio
Technology
Solar: 3.2 MW · Battery
Total requested
3.2 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
17 March 2020
Proposed online date
February 2021
Came online
June 2021

Location

Marker shows the centre of Paulding County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Paulding County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem