United States › Grid › Interconnection queues › Ohio

ONSHORE WIND · PJM

Trishe Wind Ohio, LLC

Trishe Wind Ohio, LLC is a 100 MW onshore wind request built and operating in the PJM interconnection queue, in Paulding County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Feb 2009 (completed)
  2. ConsentedOct 2014 (completed)
  3. Construction (completed)
  4. OperatingSep 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
V1-011
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Haviland 138kV
Location
Paulding County, Ohio
Technology
Wind: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
26 February 2009
Agreement signed
3 October 2014
Proposed online date
December 2018
Came online
September 2018

Location

Marker shows the centre of Paulding County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Paulding County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem