United States βΊ Grid βΊ Interconnection queues βΊ Ohio
ONSHORE WIND Β· PJMOnshore wind project S117, Paulding County
Onshore wind project S117, Paulding County is a 150 MW onshore wind request withdrawn in the PJM interconnection queue, in Paulding County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2007 (completed)
- Withdrawn / abandonedSep 2007 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- S117
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Haviland 138kV
- Location
- Paulding County, Ohio
- Technology
- Wind: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 July 2007
- Proposed online date
- October 2008
- Withdrawn
- September 2007
Location
Marker shows the centre of Paulding County; the queue data does not give exact sites.
Other requests in Paulding County
- Grover Hill Wind ProjectOnshore wind Β· 140 MW Β· agreement signed
- Timber Road Storage IIIBattery storage Β· 50.0 MW Β· agreement signed
- Timber Road Solar Park IIISolar Β· 49.9 MW Β· agreement signed
- Paulding Storage IIBattery storage Β· 50.0 MW Β· in study
- Timber Road IIIOnshore wind Β· 150 MW Β· built
- Trishe Wind Ohio, LLCOnshore wind Β· 100 MW Β· built
- Timber Road II WFOnshore wind Β· 97.0 MW Β· built
- Timber Road IV Wind Farm (Southern Phase)Onshore wind Β· 75.9 MW Β· built
- Timber Road Solar ParkSolar Β· 49.9 MW Β· built
- Northwest Ohio WindSolar + storage Β· 3.2 MW Β· built
- Onshore wind project T130, Paulding CountyOnshore wind Β· 300 MW Β· withdrawn
- Trishe Wind Ohio, LLCOnshore wind Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem