United States › Grid › Interconnection queues › Ohio

ONSHORE WIND · PJM

Timber Road IV Wind Farm (Southern Phase)

Timber Road IV Wind Farm (Southern Phase) is a 75.9 MW onshore wind request built and operating in the PJM interconnection queue, in Paulding County, Ohio, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Oct 2016 (completed)
  2. ConsentedDec 2019 (completed)
  3. Construction (completed)
  4. OperatingMar 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AC1-173
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Logtown 138kV
Location
Paulding County, Ohio
Technology
Wind: 75.9 MW
Total requested
75.9 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
31 October 2016
Agreement signed
26 December 2019
Proposed online date
March 2020
Came online
March 2020

Location

Marker shows the centre of Paulding County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Paulding County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem