United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Solar project W2-071, Burlington County

Solar project W2-071, Burlington County is a 2.8 MW solar request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jul 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
W2-071
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Mt. Laurel 13kV
Location
Burlington County, New Jersey
Technology
Solar: 2.8 MW
Total requested
2.8 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
30 July 2010
Proposed online date
October 2011
Came online
December 2011

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem