Burlington #10

Burlington #10 is a 16.0 MW gas request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Apr 2001 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G17
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Burlington
Location
Burlington County, New Jersey
Technology
Gas: 16.0 MW
Total requested
16.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
5 April 2001
Proposed online date
July 2002
Came online
July 2002

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem