🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

North Hanover Solar Farm

North Hanover Solar Farm is a 17.0 MW solar request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to JCPL.

Queue statusOperating
  1. PlanningQueued Jul 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingMar 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
W2-082
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
JCPL
Connection point (POI)
Fort Dix-McGuire 34.5kV
Location
Burlington County, New Jersey
Technology
Solar: 17.0 MW
Total requested
17.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
30 July 2010
Proposed online date
January 2017
Came online
March 2017

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem