🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › New Jersey

SOLAR · PJM

Burlington (L&D Solar) 26kV

Burlington (L&D Solar) 26kV is a 10.0 MW solar request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Jan 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-026
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Burlington 26kV
Location
Burlington County, New Jersey
Technology
Solar: 10.0 MW
Total requested
10.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
25 January 2013
Proposed online date
September 2015
Came online
January 2016

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem