Brookside Energy Center

Brookside Energy Center is a 3.0 MW other request built and operating in the PJM interconnection queue, in New Castle County, Delaware, connecting to DPL.

Queue statusOperating
  1. PlanningQueued Jul 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
X2-083
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Newark 12kV
Location
New Castle County, Delaware
Technology
Other: 3.0 MW
Total requested
3.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
29 July 2011
Proposed online date
August 2012
Came online
June 2012

Location

Marker shows the centre of New Castle County; the queue data does not give exact sites.

Power plants in Delaware · Transmission lines in Delaware

Other requests in New Castle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem