Hay Road 5, 6, 7

Hay Road 5, 6, 7 is a 545 MW gas request built and operating in the PJM interconnection queue, in New Castle County, Delaware, connecting to DPL.

Queue statusOperating
  1. PlanningQueued Nov 1999 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJul 2002 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
B47
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DPL
Connection point (POI)
Red Lion 500kV
Location
New Castle County, Delaware
Technology
Gas: 545 MW
Total requested
545 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
29 November 1999
Proposed online date
July 2002
Came online
July 2002

Location

Marker shows the centre of New Castle County; the queue data does not give exact sites.

Power plants in Delaware · Transmission lines in Delaware

Other requests in New Castle County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem