SOLAR · PJM

Beaverbrook (Kinsley Solar)

Beaverbrook (Kinsley Solar) is a 3.8 MW solar request built and operating in the PJM interconnection queue, in Gloucester County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Apr 2013 (completed)
  2. ConsentedJun 2014 (completed)
  3. Construction (completed)
  4. OperatingJan 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-087
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Beaverbrook 13kV
Location
Gloucester County, New Jersey
Technology
Solar: 3.8 MW
Total requested
3.8 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
26 April 2013
Agreement signed
11 June 2014
Proposed online date
June 2015
Came online
January 2015

Location

Marker shows the centre of Gloucester County; the queue data does not give exact sites.

Power plants in New Jersey · Transmission lines in New Jersey

Other requests in Gloucester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem