United States › Grid › Interconnection queues › Pennsylvania
ONSHORE WIND · PJMTurkey Hill Dairy WF
Turkey Hill Dairy WF is a 3.2 MW onshore wind request built and operating in the PJM interconnection queue, in Lancaster County, Pennsylvania, connecting to PPL.
Request details
- Queue ID
- V3-051
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PPL
- Connection point (POI)
- Letort
- Location
- Lancaster County, Pennsylvania
- Technology
- Wind: 3.2 MW
- Total requested
- 3.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 16 October 2009
- Proposed online date
- January 2011
- Came online
- January 2011
Location
Marker shows the centre of Lancaster County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Lancaster County
- HoltwoodHydro · 140 MW · built
- HoltwoodHydro · 107 MW · built
- Dart ContainerOther · 11.4 MW · built
- YorkGas · 10.0 MW · built
- Keystone SolarSolar · 5.0 MW · built
- HoltwoodHydro · 2.0 MW · built
- Granger of HoneybrookOther · 1.6 MW · built
- Sight and Sound TheaterGas · 1.6 MW · built
- ElizabethtownGas · 0.3 MW · built
- Gas project AA2-109, Lancaster CountyGas · 1,100 MW · withdrawn
- Gas project U1-016, Lancaster CountyGas · 700 MW · withdrawn
- Gas project U2-074, Lancaster CountyGas · 650 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem