United States βΊ Grid βΊ Interconnection queues βΊ Michigan
OTHER Β· PJMOrchard Hills
Orchard Hills is a 3.2 MW other request built and operating in the PJM interconnection queue, in Berrien County, Michigan, connecting to AEP.
Request details
- Queue ID
- X1-042
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Watervliet
- Location
- Berrien County, Michigan
- Technology
- Other: 3.2 MW
- Total requested
- 3.2 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 29 March 2011
- Proposed online date
- November 2012
- Came online
- March 2013
Location
Marker shows the centre of Berrien County; the queue data does not give exact sites.
Other requests in Berrien County
- Solar + storage project AH2-373, Berrien CountySolar + storage Β· 180 MW Β· in study
- Solar + storage project AH2-418, Berrien CountySolar + storage Β· 100 MW Β· in study
- D.C. Cook Generating Plant Unit No. 2Nuclear Β· 102 MW Β· built
- Cook #1Nuclear Β· 84.0 MW Β· built
- DC Cook Generating Plant Unit No. 2Nuclear Β· 38.0 MW Β· built
- Southeast Berrien LFOther Β· 6.4 MW Β· built
- Watervliet Solar FacilitySolar Β· 4.6 MW Β· built
- Orchard Hills Sanitary LandfillOther Β· 0.8 MW Β· built
- Gas project N46, Berrien CountyGas Β· 1,120 MW Β· withdrawn
- Onshore wind project J632, Berrien CountyOnshore wind Β· 200 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem