United States › Grid › Interconnection queues › Michigan
OTHER · PJMSoutheast Berrien LF
Southeast Berrien LF is a 6.4 MW other request built and operating in the PJM interconnection queue, in Berrien County, Michigan, connecting to AEP.
Request details
- Queue ID
- T111
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Buchanan Hydro-Niles 69kV
- Location
- Berrien County, Michigan
- Technology
- Other: 6.4 MW
- Total requested
- 6.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 12 December 2007
- Agreement signed
- 31 July 2008
- Proposed online date
- May 2009
- Came online
- May 2009
Location
Marker shows the centre of Berrien County; the queue data does not give exact sites.
Other requests in Berrien County
- Solar + storage project AH2-373, Berrien CountySolar + storage · 180 MW · in study
- Solar + storage project AH2-418, Berrien CountySolar + storage · 100 MW · in study
- D.C. Cook Generating Plant Unit No. 2Nuclear · 102 MW · built
- Cook #1Nuclear · 84.0 MW · built
- DC Cook Generating Plant Unit No. 2Nuclear · 38.0 MW · built
- Watervliet Solar FacilitySolar · 4.6 MW · built
- Orchard HillsOther · 3.2 MW · built
- Orchard Hills Sanitary LandfillOther · 0.8 MW · built
- Gas project N46, Berrien CountyGas · 1,120 MW · withdrawn
- Onshore wind project J632, Berrien CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem