πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί New Jersey

SOLAR Β· PJM

Mill Creek

Mill Creek is a 3.5 MW solar request built and operating in the PJM interconnection queue, in Burlington County, New Jersey, connecting to PSEG.

Queue statusOperating
  1. PlanningQueued Apr 2011 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2011 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
X1-070
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PSEG
Connection point (POI)
Levittown 138kV
Location
Burlington County, New Jersey
Technology
Solar: 3.5 MW
Total requested
3.5 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
25 April 2011
Proposed online date
January 2012
Came online
September 2011

Location

Marker shows the centre of Burlington County; the queue data does not give exact sites.

Power plants in New Jersey Β· Transmission lines in New Jersey

Other requests in Burlington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem