Wabash Valley Power Association, Inc.

Wabash Valley Power Association, Inc. is a 3.2 MW other request built and operating in the PJM interconnection queue, in Jay County, Indiana, connecting to AEP.

Queue statusOperating
  1. PlanningQueued Jan 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y3-024
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Connection point (POI)
Bluff Point 12kV
Location
Jay County, Indiana
Technology
Other: 3.2 MW
Total requested
3.2 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
Queue status
Operational
Entered queue
18 January 2013
Proposed online date
June 2015
Came online
January 2015

Location

Marker shows the centre of Jay County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Jay County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem