United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Completed queue projects in the USA (2012 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown17617.9 GW
Active in queue1,925 MW19 requests
Agreement signed152 MW7 requests
Withdrawn39770.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

176 requests ยท page 2 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Copenhagen Wind
Onshore wind ยท Copenhagen Wind Farm, LLC
79.9 MWOperating Lewis, NYNYISO Nov 20122019
Copenhagen Wind
Onshore wind ยท Copenhagen Wind Farm, LLC
79.9 MWOperating NYNYISO Nov 2012
Jericho Rise Wind
Onshore wind ยท Jericho Rise Wind Farm, LLC
77.7 MWOperating NYNYISO Dec 2012
Jericho Rise Wind
Onshore wind ยท Jericho Rise Wind Farm, LLC
77.7 MWOperating Franklin, NYNYISO Dec 20122017
Onshore wind project GEN-2012-028, Washita County
Onshore wind
74.0 MWOperating Washita, OKSPP Sep 20122015
Liberty Electric
Gas
65.5 MWOperating Delaware, PAPJM Sep 20122015
Windthorst 2
Onshore wind ยท OwnEnergy
65.0 MWOperating ERCOT Jun 20122014
Solar project 4910, Duplin County
Solar ยท Duke Energy Progress, LLC
64.8 MWOperating Duplin, NCSoutheast Apr 20122015
Eagle Point
Gas
63.0 MWOperating Gloucester, NJPJM Nov 20122015
Onshore wind project GEN-2012-001, Lynn County
Onshore wind
61.2 MWOperating Lynn, TXSPP Mar 20122012
Nuclear project 231, Rhea County
Nuclear
57.0 MWOperating Rhea, TNSoutheast Feb 2012
Hancock Wind Project
Onshore wind
51.0 MWOperating Hancock, MEISO-NE Aug 2012target 2016
Gas project GI-1204, Mckenzie County
Gas ยท Basin Electric
50.0 MWOperating Mckenzie, NDWest Apr 2012target 2014
Gas project GI-1207, Williams County
Gas ยท Basin Electric
50.0 MWOperating Williams, NDWest May 2012target 2013
Gas project GI-1205, Williams County
Gas ยท Basin Electric
50.0 MWOperating Williams, NDWest Apr 2012target 2013
Solar project 450, Millard County
Solar ยท Pavant Solar, LLC
50.0 MWOperating Millard, UTWest Dec 2012target 2015
Pastoria Energy Facility
Gas
50.0 MWOperating Kern, CACAISO Apr 20122016
Gas project GI-1202, Mckenzie County
Gas ยท Basin Electric
50.0 MWOperating Mckenzie, NDWest Jan 2012target 2013
OCI Alamo 1
Solar ยท OCI Alamo 1 LLC
50.0 MWOperating ERCOT Aug 20122013
Gas project GI-1208, Mckenzie County
Gas ยท Basin Electric
50.0 MWOperating Mckenzie, NDWest May 2012target 2014
Newark Energy Center
Gas
45.0 MWOperating Essex, NJPJM Jun 20122015
Gas project 12-050, Columbia County
Gas
44.0 MWOperating Columbia, ORWest Feb 2012
Gas project IA-PNM-2012-02, Valencia County
Gas
42.3 MWOperating Valencia, NMWest Aug 2012
Onshore wind project GEN-2012-004, Carter County
Onshore wind
40.8 MWOperating Carter, OKSPP Mar 20122014
SPSA Navy Power Plant
Other
40.0 MWOperating City Of Portsmouth, VAPJM May 20122014
Gas project 37, Whatcom County
Gas
40.0 MWOperating Whatcom, WAWest Aug 2012target 2012
Onshore wind project Y1-033, Somerset County
Onshore wind
38.3 MWOperating Somerset, PAPJM Feb 20122016
OCI Alamo 4 (Brackettville / ECLIPSE)
Solar ยท OCI Solar Power LLC
38.0 MWOperating ERCOT Mar 20122014
Gas project 25667, Richmond County
Gas ยท Duke Energy Progress, LLC
32.0 MWOperating Richmond, NCSoutheast Jan 20122012
Hopewell Cogeneration Facility (HCF)
Gas
30.0 MWOperating City Of Hopewell, VAPJM Oct 20122017
Onshore wind project BHCT-G11, Huerfano County
Onshore wind ยท Black Hills Electric Generation LLC
29.0 MWOperating Huerfano, COWest Jun 2012target 2020
Hydro project 17108
Hydro ยท Duke Energy Carolinas LLC
27.0 MWOperating Southeast Nov 20122013
Mojave Solar
Solar
25.0 MWOperating San Bernardino, CACAISO Apr 20122015
Solar project 4904, Bladen County
Solar ยท Tangent Energy Solutions, INC.
23.0 MWOperating Bladen, NCSoutheast Aug 20122015
MeadWestvaco Covington Mill Site
Other
20.0 MWOperating VAPJM Apr 20122013
Solar project 394, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Mar 2012target 2016
Morgan's Corner Solar
Solar
20.0 MWOperating Pasquotank, NCPJM Apr 20122015
Lakewood Cogeneration Plant
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
Rochelle Plant
Gas
20.0 MWOperating Hamilton, OHPJM Apr 20122013
Ocean Peaking Power
Gas
20.0 MWOperating Ocean, NJPJM Oct 20122015
Solar project 395, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Mar 2012target 2016
Solar project 397, Elmore County
Solar
20.0 MWOperating Elmore, IDWest Jun 2012target 2016
Gas project X4-046
Gas
19.5 MWOperating DCPJM Jan 20122019
Oxbow Creek Generation Plant
Gas
18.3 MWOperating Wyoming, PAPJM Jul 20122019
EF Kenilworth LLC
Gas
17.9 MWOperating Union, NJPJM Jan 20122015
Marsh Hill Wind
Onshore wind ยท Invenergy NY LLC
16.2 MWOperating NYNYISO Mar 2012
Marsh Hill Wind
Onshore wind ยท Invenergy NY LLC
16.2 MWOperating Steuben, NYNYISO Mar 20122014
Roundtop Energy Project
Gas
15.4 MWOperating Wyoming, PAPJM Mar 20122015
Geothermal project SGI-PNM-2012-05, Hidalgo County
Geothermal
15.0 MWOperating Hidalgo, NMWest May 2012
Onshore wind project 153, Teton County
Onshore wind
15.0 MWOperating Teton, MTWest Aug 20122012

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)