United States › Grid › Interconnection queues › Oklahoma
ONSHORE WIND · SPPOnshore wind project GEN-2012-004, Carter County
Onshore wind project GEN-2012-004, Carter County is a 40.8 MW onshore wind request built and operating in the SPP interconnection queue, in Carter County, Oklahoma, connecting to OGE.
Request details
- Queue ID
- GEN-2012-004
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Pooleville-Ratliff (Carter County) 138kV
- Location
- Carter County, Oklahoma
- Technology
- Wind: 40.8 MW
- Total requested
- 40.8 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/COMMERCIAL OPERATION
- Queue status
- Operational
- Entered queue
- 27 March 2012
- Proposed online date
- November 2014
- Came online
- November 2014
Location
Marker shows the centre of Carter County; the queue data does not give exact sites.
Other requests in Carter County
- Battery storage project GEN-2024-242, Carter CountyBattery storage · 250 MW · in study
- Solar + storage project GEN-2024-337, Carter CountySolar + storage · 250 MW · in study
- Onshore wind project GEN-2017-027, Carter CountyOnshore wind · 140 MW · built
- Solar project GEN-2020-085, Carter CountySolar · 500 MW · withdrawn
- Solar + storage project GEN-2021-004, Carter CountySolar + storage · 250 MW · withdrawn
- Solar project GEN-2017-166, Carter CountySolar · 250 MW · withdrawn
- Battery storage project GEN-2020-074, Carter CountyBattery storage · 200 MW · withdrawn
- Solar project GEN-2022-042, Carter CountySolar · 174 MW · withdrawn
- Onshore wind project GEN-2010-019, Carter CountyOnshore wind · 52.2 MW · withdrawn
- Battery storage project GEN-2017-167, Carter CountyBattery storage · 52.0 MW · withdrawn
- Gas project GEN-2008-056S, Carter CountyGas · 4.8 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem