United States βΊ Grid βΊ Interconnection queues βΊ District of Columbia
GAS Β· PJMGas project X4-046
Gas project X4-046 is a 19.5 MW gas request built and operating in the PJM interconnection queue, connecting to PEPCO.
Request details
- Queue ID
- X4-046
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PEPCO
- Connection point (POI)
- E Street (Sub 18) 13kV
- Location
- District of Columbia
- Technology
- Gas: 19.5 MW
- Total requested
- 19.5 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Operational
- Entered queue
- 31 January 2012
- Proposed online date
- September 2015
- Came online
- February 2019
Location
No county location in the queue data.
Power plants in District of Columbia Β· Transmission lines in District of Columbia
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem