United States › Grid › Interconnection queues › Pennsylvania

ONSHORE WIND · PJM

Onshore wind project Y1-033, Somerset County

Onshore wind project Y1-033, Somerset County is a 38.3 MW onshore wind request built and operating in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Feb 2012 (completed)
  2. ConsentedJul 2017 (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-033
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
Penn Mar-Rock Wood 115kV
Location
Somerset County, Pennsylvania
Technology
Wind: 38.3 MW
Total requested
38.3 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
29 February 2012
Agreement signed
13 July 2017
Proposed online date
March 2017
Came online
December 2016

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem