GAS Β· PJM

Rochelle Plant

Rochelle Plant is a 20.0 MW gas request built and operating in the PJM interconnection queue, in Hamilton County, Ohio, connecting to DEOK.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. ConsentedDec 2012 (completed)
  3. Construction (completed)
  4. OperatingMay 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-054
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Rochelle 138kV
Location
Hamilton County, Ohio
Technology
Gas: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
16 April 2012
Agreement signed
21 December 2012
Proposed online date
May 2013
Came online
May 2013

Location

Marker shows the centre of Hamilton County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Hamilton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem