United States › Grid › Interconnection queues › Ohio

BATTERY STORAGE · PJM

Willey Energy Storage Project

Willey Energy Storage Project is a 6.0 MW battery storage request built and operating in the PJM interconnection queue, in Hamilton County, Ohio, connecting to DEOK.

Queue statusOperating
  1. PlanningQueued Sep 2013 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Z1-065
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
DEOK
Connection point (POI)
Wiley 34.5kV
Location
Hamilton County, Ohio
Technology
Battery: 6.0 MW
Total requested
6.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
Queue status
Operational
Entered queue
30 September 2013
Proposed online date
November 2015
Came online
December 2015

Location

Marker shows the centre of Hamilton County; the queue data does not give exact sites.

Power plants in Ohio · Transmission lines in Ohio

Other requests in Hamilton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem