Roundtop Energy Project

Roundtop Energy Project is a 15.4 MW gas request built and operating in the PJM interconnection queue, in Wyoming County, Pennsylvania, connecting to PENELEC.

Queue statusOperating
  1. PlanningQueued Mar 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-047
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Connection point (POI)
North Meshoppen 34.5kV
Location
Wyoming County, Pennsylvania
Technology
Gas: 15.4 MW
Total requested
15.4 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
30 March 2012
Proposed online date
April 2015
Came online
October 2015

Location

Marker shows the centre of Wyoming County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Wyoming County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem