United States β€Ί Grid β€Ί Interconnection queues β€Ί Virginia

OTHER Β· PJM

MeadWestvaco Covington Mill Site

MeadWestvaco Covington Mill Site is a 20.0 MW other request built and operating in the PJM interconnection queue, connecting to Dominion.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingOct 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Y1-068
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Connection point (POI)
East Mill 138kV
Location
Virginia
Technology
Other: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
27 April 2012
Proposed online date
June 2014
Came online
October 2013

Location

No county location in the queue data.

Power plants in Virginia Β· Transmission lines in Virginia