🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

GAS · CAISO

Pastoria Energy Facility

Pastoria Energy Facility is a 50.0 MW gas request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusOperating
  1. PlanningQueued Apr 2012 (completed)
  2. ConsentedOct 2015 (completed)
  3. Construction (completed)
  4. OperatingApr 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
911
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Pastoria Substation 220kV
Location
Kern County, California
Technology
Gas: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
2 April 2012
Agreement signed
1 October 2015
Proposed online date
January 2014
Came online
April 2016

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem