Completed queue projects in the USA (2010 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown23515.8 GW
Active in queue2,652 MW13 requests
Agreement signed1,364 MW9 requests
Withdrawn1,016100.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

235 requests ยท page 2 of 5
ProjectCapacityStatusLocationRegionQueuedOnline
Hilltopper Wind, LLC
Onshore wind
62.5 MWOperating Logan, ILPJM Jun 20102018
Onshore wind project J122, Huron County
Onshore wind
60.0 MWOperating Huron, MIMISO Apr 20102012
Solar project Q11, Kern County
Solar
60.0 MWOperating Kern, CAWest Mar 20102016
Regulus Solar (Fka FRV Regulus Solar)
Solar
60.0 MWOperating Kern, CACAISO Feb 20102014
Warren County
Gas
60.0 MWOperating Warren, VAPJM Aug 20102014
Gas project GI-1004, Brown County
Gas ยท Northwestern Energy
60.0 MWOperating Brown, SDWest Mar 2010target 2013
Lund Hill
Solar ยท Pacific Wind Development, LLC
60.0 MWOperating Klickitat, WAWest Apr 2010target 2020
North Star Solar 1
Solar
60.0 MWOperating Fresno, CACAISO Feb 20102015
Gas project J142, Wood County
Gas
59.7 MWOperating Wood, WIMISO Jun 2010target 2011
Smyrna Units 1 & 2
Gas
53.0 MWOperating Kent, DEPJM Mar 20102012
Onshore wind project G997, Huron County
Onshore wind
50.0 MWOperating Huron, MIMISO Dec 20102009
Hope Creek Generating Station
Nuclear
50.0 MWOperating Salem, NJPJM Aug 20102013
Groton Wind Farm
Onshore wind
48.0 MWOperating Grafton, NHISO-NE Sep 2010target 2012
South Boston Energy Facility
Other
47.4 MWOperating Halifax, VAPJM Jun 20102013
TAMU Combined Heat & Power
Gas ยท Texas A&M
45.0 MWOperating ERCOT Apr 2010target 2011
Centinela Solar Energy Expansion (45 MW)
Solar
45.0 MWOperating Imperial, CACAISO Jul 20102014
Gas project J174, Jefferson County
Gas
43.8 MWOperating Jefferson, WIMISO Nov 20102011
Gas project ASGI-2010-010
Gas
42.0 MWOperating SPP Jan 20102012
Troy Energy
Gas
40.0 MWOperating Wood, OHPJM Apr 20102014
Onshore wind project 334, Twin Falls County
Onshore wind
40.0 MWOperating Twin Falls, IDWest Jun 20102012
Coal project J143, Ontonagon County
Coal
40.0 MWOperating Ontonagon, MIMISO Jun 2010
Gas project BHCT-G6, Pueblo County
Gas ยท Black Hills Electric Generation LLC
40.0 MWOperating Pueblo, COWest Dec 2010target 2016
Onshore wind project 335, Converse County
Onshore wind ยท Pioneer Wind Park I, LLC
40.0 MWOperating Converse, WYWest Jun 2010target 2016
Onshore wind project GI-1003, Jerauld County
Onshore wind ยท PrairieWinds SD1 Inc.
34.0 MWOperating Jerauld, SDWest Feb 2010target 2010
S_Hills Wind
Onshore wind ยท SEYMOUR HILLS WIND PROJECT, LLC
30.2 MWOperating Baylor, TXERCOT Sep 20102019
Onshore wind project GEN-2010-011, Dewey County
Onshore wind
29.7 MWOperating Dewey, OKSPP Mar 20102012
Gas project W4-010, Montgomery County
Gas
29.1 MWOperating Montgomery, MDPJM Nov 20102014
Laurel Mountain BT
Battery storage
27.4 MWOperating Barbour, WVPJM Jul 20102011
Spi Anderson 2
Other
27.2 MWOperating CACAISO Jul 20102015
Verso Androscoggin Energy Cogen 1, 2, & 3 Increase
Gas
26.0 MWOperating Franklin, MEISO-NE May 2010target 2012
Bucksport G5
Other
25.0 MWOperating Hancock, MEISO-NE Oct 2010target 2012
Russell City Energy Center FD3 Upgrade
Gas
25.0 MWOperating Alameda, CACAISO Feb 20102013
Hudson Generating Station
Coal
24.0 MWOperating Hudson, NJPJM Dec 20102012
Onshore wind project 126, Judith Basin County
Onshore wind
24.0 MWOperating Judith Basin, MTWest Oct 20102011
Barilla Solar
Solar ยท First Solar
22.0 MWOperating ERCOT Dec 20102015
Onshore wind project 317, Elmore County
Onshore wind
22.0 MWOperating Elmore, IDWest Feb 20102011
Onshore wind project 323-A, Power County
Onshore wind ยท Power County Wind Park North, LLC
21.6 MWOperating Power, IDWest Mar 2010target 2011
Onshore wind project 323-B, Power County
Onshore wind ยท Power County Wind Park South, LLC
21.6 MWOperating Power, IDWest Mar 2010target 2011
Onshore wind project 357, Twin Falls County
Onshore wind
21.0 MWOperating Twin Falls, IDWest Oct 20102011
Solar project Q20, Pinal County
Solar
20.0 MWOperating Pinal, AZWest Nov 20102012
Adobe Solar (Fka FRV Adobe Solar)
Solar
20.0 MWOperating Kern, CACAISO May 20102014
Western Antelope Blue SKY Ranch A
Solar
20.0 MWOperating Los Angeles, CACAISO Dec 20102014
Onshore wind project 339, Elmore County
Onshore wind
20.0 MWOperating Elmore, IDWest Jun 20102012
Kansas South
Solar
20.0 MWOperating Kings, CACAISO Jul 20102013
Wildwood Solar I (Fka Goose Lake Solar I)
Solar
20.0 MWOperating Kern, CACAISO Oct 20102015
Kansas
Solar
20.0 MWOperating Kings, CACAISO Jul 20102014
Jacumba Solar Farm
Solar
20.0 MWOperating San Diego, CACAISO Aug 20102017
Beacon Power Flywheel Station
Battery storage
20.0 MWOperating Luzerne, PAPJM Apr 20102014
Oak Hall Project C
Solar
20.0 MWOperating VAPJM Feb 20102016
Vega Solar (Fka: FRV Vega Solar)
Solar
20.0 MWOperating Kings, CACAISO Jan 20102015

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)