SOLAR Β· PJMOak Hall Project C
Oak Hall Project C is a 20.0 MW solar request built and operating in the PJM interconnection queue, connecting to DPL.
Request details
- Queue ID
- W1-005
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DPL
- Connection point (POI)
- Oak Hall
- Location
- Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 4 February 2010
- Proposed online date
- December 2017
- Came online
- December 2016
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem