Onshore wind project 335, Converse County

Onshore wind project 335, Converse County is a 40.0 MW onshore wind request built and operating in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Jun 2010 (completed)
  2. ConsentedMay 2013 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
335
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Pioneer Wind Park I, LLC
Connection point (POI)
Amassa substation, (DJ - Difficulty)
Location
Converse County, Wyoming
Technology
Wind: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
IA signed May 1, 2013
Queue status
Operational
Entered queue
1 June 2010
Agreement signed
1 May 2013
Proposed online date
October 2016

Location

Marker shows the centre of Converse County; the queue data does not give exact sites.