🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR · WEST

Solar project Q11, Kern County

Solar project Q11, Kern County is a 60.0 MW solar request built and operating in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusOperating
  1. PlanningQueued Mar 2010 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingAug 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q11
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Barren Ridge 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
1 March 2010
Proposed online date
June 2015
Came online
August 2016

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem