πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Kansas South

Kansas South is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Jul 2010 (completed)
  2. ConsentedMar 2012 (completed)
  3. Construction (completed)
  4. OperatingJun 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
637
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Henrietta-Jacobs Corner 70kV
Location
Kings County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
6 July 2010
Agreement signed
9 March 2012
Proposed online date
December 2012
Came online
June 2013

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem