United States › Grid › Interconnection queues › California

SOLAR · CAISO

Wildwood Solar I (Fka Goose Lake Solar I)

Wildwood Solar I (Fka Goose Lake Solar I) is a 20.0 MW solar request built and operating in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Oct 2010 (completed)
  2. ConsentedApr 2013 (completed)
  3. Construction (completed)
  4. OperatingFeb 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
654
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Semitropic-Midway #2 115kV
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
25 October 2010
Agreement signed
9 April 2013
Proposed online date
May 2013
Came online
February 2015

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem