United States › Grid › Interconnection queues › California

SOLAR · CAISO

North Star Solar 1

North Star Solar 1 is a 60.0 MW solar request built and operating in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusOperating
  1. PlanningQueued Feb 2010 (completed)
  2. ConsentedJul 2013 (completed)
  3. Construction (completed)
  4. OperatingJun 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
607
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Mendota Substation 115 kV bus
Location
Fresno County, California
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
1 February 2010
Agreement signed
31 July 2013
Proposed online date
October 2012
Came online
June 2015

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem