United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in Texas (2024 requests) — page 2
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ulysses Crossing Solar Solar |
405 MW | Paused / redesign |
| Big Rooter West Solar Solar + storage · Big Rooter West, LLC |
403 MW | Agreement signed |
| Hittson Creek Solar Solar + storage · 174 Power Global Properties |
403 MW | In study |
| Solarville Solar SLF Solar + storage · Ville Solar, LLC |
403 MW | In study |
| Bernice Energy Storage Battery storage · Bernice Energy Storage LLC |
403 MW | In study |
| Bluefox Solar 1 Solar · Industrial November Project LLC |
403 MW | In study |
| Bluefox Solar 2 Solar · Industrial November Project LLC |
402 MW | In study |
| Infinium Solar Solar · Jackalope Flats Solar, LLC |
402 MW | In study |
| Corruscant BESS Battery storage · AEU Battery Project III LLC |
402 MW | In study |
| Biggs Solar Solar + storage · Biggs Solar Farm, LLC |
400 MW | In study |
| Paint Rock Wind Onshore wind · Orsted Onshore Development North America, LLC |
379 MW | In study |
| Skyrider Wind Onshore wind · NextEra Energy Interconnection Holdings, LLC |
370 MW | In study |
| Twinwood Solar 1 Solar · Twinwood PV1, LLC |
358 MW | In study |
| West Munday Wind Onshore wind · Lake Creek Wind, LLC |
352 MW | Agreement signed |
| Funston Solar Solar · Funston Solar LLC |
351 MW | Agreement signed |
| Solar project GEN-2024-046, Hansford County Solar |
345 MW | In study |
| Solar project GEN-2024-045, Hansford County Solar |
345 MW | In study |
| Rabbit Hollow Energy Storage Battery storage · Rabbit Hollow Energy Storage, LLC |
342 MW | In study |
| Three Canes Solar SLF Solar · Three Canes Solar LLC |
333 MW | Agreement signed |
| Sky Global West Houston Gas · Sky Global Power Two, LLC |
325 MW | Agreement signed |
| Quantum Storage Solar + storage · IP Quantum II BESS, LLC |
322 MW | Agreement signed |
| Solace Storage Solar + storage · IP Quantum BESS, LLC |
322 MW | Agreement signed |
| Andromeda Storage II Battery storage |
320 MW | Paused / redesign |
| Andromeda Storage IIB Battery storage |
320 MW | Paused / redesign |
| Radian Storage II Battery storage |
320 MW | Paused / redesign |
| Jade Thunder Storage Battery storage |
320 MW | Paused / redesign |
| Jade Flash Storage Battery storage |
320 MW | Paused / redesign |
| Radian Storage IIB Battery storage |
320 MW | Paused / redesign |
| Diablo Campo Storage Battery storage · Diablo Campo Energy Center, LLC |
314 MW | In study |
| Wild Paw Storage Battery storage · Wild Paw Energy Center, LLC |
313 MW | In study |
| Sunrose Renewable Energy Solar SLF Solar + storage · Sunrose Renewable Energy LLC |
310 MW | In study |
| Red Hollow Renewable Energy Solar SLF Solar + storage · Red Hollow Renewable Energy LLC |
309 MW | In study |
| Clay County Yang Storage Battery storage · DM-CCY, LLC |
308 MW | In study |
| Team Ranch Storage Battery storage · BAF Storage, LLC |
307 MW | In study |
| Cattle Drive Solar Solar · NextEra Energy Interconnection Holdings, LLC |
307 MW | In study |
| Axtell BESS Battery storage · Axtell BESS LLC |
307 MW | In study |
| Copperleaf Energy Storage Battery storage · Copperleaf Energy Storage, LLC |
307 MW | In study |
| Gilleys Energy Storage Battery storage · Gilleys Energy Storage, LLC |
306 MW | In study |
| McCrae Energy Storage Battery storage · McCrae Energy Storage, LLC |
306 MW | Agreement signed |
| O'Bannion Energy Storage Battery storage · O'Bannion Energy Storage, LLC |
306 MW | Agreement signed |
| Wooderson Energy Storage Battery storage · Wooderson Energy Storage, LLC |
306 MW | In study |
| Southfork Energy Storage Battery storage · Southfork Energy Storage, LLC |
306 MW | In study |
| Straight Spur Storage Solar + storage · ENGIE IR Holdings LLC |
306 MW | In study |
| Bullring Wind 2 Onshore wind · Halcon Wind, LLC |
304 MW | Agreement signed |
| Bullring Wind 1 Onshore wind · Halcon Wind, LLC |
304 MW | Agreement signed |
| Wander Waters BESS Battery storage · Wander Waters BESS LLC |
304 MW | In study |
| Uva Creek Solar Solar · Grape Creek Solar, LLC |
302 MW | Agreement signed |
| Silver Dollar Solar Solar + storage · Silver Dollar Solar Project, LLC |
302 MW | In study |
| Winters Glow Solar Solar + storage · Winters Glow Solar, LLC |
302 MW | In study |
| Sunburst Solar Solar + storage · Indigo Solar, LLC |
302 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)432 · 104.7 GW
- SPP (Southwest Power Pool)13 · 3,601 MW
- MISO (Midcontinent)3 · 716 MW
- West (non-ISO utilities)4 · 550 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)