United States › Grid › Interconnection queues › California

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in California, West — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8830.3 GW
Active in queue30.3 GW88 requests
Agreement signed550 MW2 requests
Withdrawn8819.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

88 requests · page 2 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Geothermal project GI-2023-176, Imperial County
Geothermal
157 MWIn study Imperial, CAWest Apr 2023target 2029
Solar + storage project 30, Sacramento County
Solar + storage
156 MWIn study Sacramento, CAWest Dec 2022target 2029
Solar + storage project GI-2023-175, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Battery storage project 27, Sacramento County
Battery storage
150 MWIn study Sacramento, CAWest Oct 2022target 2027
Battery storage project T2-072, Siskiyou County
Battery storage
150 MWIn study Siskiyou, CAWest Sep 2025target 2027
Solar + storage project GI-2023-173, Imperial County
Solar + storage
150 MWIn study Imperial, CAWest Apr 2023target 2028
Solar project GI-2023-170, Imperial County
Solar
150 MWIn study Imperial, CAWest Apr 2023target 2026
Battery storage project GI-2021-145, Riverside County
Battery storage
125 MWIn study Riverside, CAWest Aug 2021target 2027
Solar + storage project GI-2022-163, Riverside County
Solar + storage
125 MWIn study Riverside, CAWest Sep 2022target 2025
Solar + storage project 2024-G2, Shasta County
Solar + storage
125 MWIn study Shasta, CAWest Nov 2024target 2028
Solar + storage project 2023-G4, Butte County
Solar + storage
100 MWIn study Butte, CAWest Aug 2023target 2028
Solar + storage project GI-2023-171, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Apr 2023target 2026
Solar + storage project GI-2022-154, Imperial County
Solar + storage
100 MWIn study Imperial, CAWest Feb 2022target 2024
Battery storage project GI-2023-166, Imperial County
Battery storage
100 MWIn study Imperial, CAWest Jan 2023target 2024
Battery storage project Q110, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Battery storage project 25, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Aug 2022target 2027
Battery storage project GI-2022-153, Riverside County
Battery storage
100 MWIn study Riverside, CAWest Jan 2022target 2024
Battery storage project Q109, Los Angeles County
Battery storage
100 MWIn study Los Angeles, CAWest Jun 2024target 2027
Battery storage project 15, Sacramento County
Battery storage
100 MWIn study Sacramento, CAWest Dec 2021target 2027
Battery storage project GI-2023-169, Imperial County
Battery storage
90.0 MWIn study Imperial, CAWest Apr 2023target 2025
Solar + storage project GI-2021-148, Imperial County
Solar + storage
90.0 MWIn study Imperial, CAWest Nov 2021target 2027
Other project GI-2020-139, Riverside County
Other
80.0 MWIn study Riverside, CAWest Nov 2020target 2027
Battery storage project GI-2023-178, Imperial County
Battery storage
75.0 MWIn study Imperial, CAWest Jun 2023target 2025
Battery storage project Q62, Los Angeles County
Battery storage
75.0 MWIn study Los Angeles, CAWest Oct 2017target 2020
Battery storage project GI-2021-146, Imperial County
Battery storage
75.0 MWIn study Imperial, CAWest Nov 2021target 2025
Solar + storage project GI-2021-147, Imperial County
Solar + storage
75.0 MWIn study Imperial, CAWest Nov 2021target 2024
Solar + storage project GI-2022-157, Imperial County
Solar + storage
65.0 MWIn study Imperial, CAWest Sep 2022target 2024
Battery storage project GI-2022-161, Imperial County
Battery storage
60.0 MWIn study Imperial, CAWest Sep 2022target 2024
Solar + storage project GI-2022-160, Imperial County
Solar + storage
50.0 MWIn study Imperial, CAWest Sep 2022target 2024
Solar + storage project GI-2023-165, Imperial County
Solar + storage
50.0 MWIn study Imperial, CAWest Jan 2023target 2025
Geothermal project GI-2020-130, Imperial County
Geothermal
50.0 MWIn study Imperial, CAWest Jan 2020target 2028
Solar + storage project GI-2022-159, Imperial County
Solar + storage
50.0 MWIn study Imperial, CAWest Sep 2022target 2024
Solar + storage project GI-2023-172, Imperial County
Solar + storage
39.2 MWIn study Imperial, CAWest Apr 2023target 2025
Solar + storage project GI-2022-158, Imperial County
Solar + storage
35.0 MWIn study Imperial, CAWest Sep 2022target 2024
Gas project GI-2025-179, Imperial County
Gas
34.8 MWIn study Imperial, CAWest Feb 2025target 2027
Geothermal project GI-2023-177, Imperial County
Geothermal
33.0 MWIn study Imperial, CAWest Apr 2023target 2026
Other project GI-2021-144, Imperial County
Other
28.0 MWIn study Imperial, CAWest Mar 2021target 2028
Solar + storage project T2-078, Modoc County
Solar + storage
24.9 MWIn study Modoc, CAWest Sep 2025target 2026
Page 2 of 2

Capacity in the queue by state

Click a state to drill down.

By grid region

ISO/RTO markets and the non-ISO West and Southeast.

Requests by year joined

Capacity of requests in this view, by the year they entered the queue. Click a year.

20122025

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)