Interconnection queue in PJM (Mid-Atlantic, Midwest) (2020 requests) โ€” page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown17816.6 GW
Active in queue16.6 GW178 requests
Agreement signed11.1 GW128 requests
Withdrawn71947.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

178 requests ยท page 2 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Summer Shade Solar
Solar + storage ยท Summer Shade Solar, LLC
106 MWAgreement signed Metcalfe, KYPJM Sep 2020target 2028
Butterfly Meadows
Battery storage ยท Butterfly Meadows Solar Project, LLC
100 MWIn study Van Wert, OHPJM Sep 2020target 2024
Flatrock Creek Solar II
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Swift Creek Solar
Solar + storage
100 MWAgreement signed Edgecombe, NCPJM Mar 2020target 2029
Prairie Creek Wind Phase 2
Onshore wind ยท Prairie Creek Wind Farm II, LLC
100 MWAgreement signed Blackford, INPJM Sep 2020target 2029
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Steward Creek Solar
Solar ยท Steward Creek Solar, LLC
100 MWIn study Lee, ILPJM Mar 2020target 2023
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Nicholas Solar
Solar
100 MWAgreement signed Nicholas, WVPJM Mar 2020target 2029
New Haven Solar
Solar
100 MWAgreement signed Mason, WVPJM Mar 2020target 2028
Remington BESS
Battery storage
100 MWAgreement signed Fauquier, VAPJM Sep 2020target 2029
Sun Chief Solar Farm
Solar
100 MWAgreement signed Jay, INPJM Jul 2020target 2027
Grand Marsh Solar
Solar ยท Deriva Energy Solar, LLC
100 MWIn study Kankakee, ILPJM Mar 2020target 2023
Red Maple Solar
Solar ยท Red Maple Solar, LLC
95.1 MWIn study Dekalb, ILPJM Aug 2020target 2023
Black Moshannon Solar
Solar + storage ยท CE-Black Moshannon OZ LLC
95.0 MWAgreement signed Centre, PAPJM Aug 2020target 2023
Red Maple Solar
Solar
94.9 MWAgreement signed Adams, ILPJM Mar 2020target 2028
Wild Rose Solar Project
Solar ยท Wild Rose Solar Project, LLC
90.0 MWIn study Nelson, VAPJM Aug 2020target 2024
Clover Creek Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
90.0 MWAgreement signed Halifax, VAPJM Aug 2020target 2030
Bear Island Solar
Solar + storage
89.0 MWAgreement signed Surry, VAPJM Mar 2020target 2028
Blossom Solar
Solar
88.0 MWAgreement signed Morrow, OHPJM Mar 2020target 2027
Harvey Solar I
Solar
85.0 MWAgreement signed Licking, OHPJM Jun 2020target 2029
Prairie Flyer Energy Storage
Battery storage
85.0 MWAgreement signed Montgomery, OHPJM Sep 2020target 2028
Carnation
Solar
84.0 MWAgreement signed Fairfield, OHPJM Mar 2020target 2028
Stonecrop Solar
Solar ยท CPV Stonecrop Solar, LLC
82.0 MWAgreement signed Hardin, KYPJM Sep 2020target 2029
Bright Mountain Solar
Solar
80.0 MWAgreement signed Perry, KYPJM Jul 2020target 2027
Frasier Solar
Solar
80.0 MWAgreement signed Knox, OHPJM Mar 2020target 2028
Walker Solar Two
Solar
80.0 MWAgreement signed Juniata, PAPJM Mar 2020target 2026
Franklintown Farm Solar and BESS
Solar + storage
80.0 MWAgreement signed Jefferson, WVPJM Sep 2020target 2028
Currituck Solar
Solar ยท Currituck Solar, LLC
80.0 MWAgreement signed Currituck, NCPJM Jan 2020target 2031
Fall Creek Energy Storage
Battery storage
80.0 MWAgreement signed Madison, INPJM Mar 2020target 2028
Brunswick Battery Storage
Battery storage ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
75.0 MWIn study Brunswick, VAPJM Sep 2020target 2031
Cerulean Solar and Mulberry BESS
Battery storage ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
75.0 MWAgreement signed Richmond, VAPJM Sep 2020target 2031
Buchanan County Solar
Solar
75.0 MWAgreement signed Buchanan, VAPJM Mar 2020target 2028
BR Solar Sheriff 1
Solar
75.0 MWAgreement signed Grant, INPJM Sep 2020target 2028
Fiddlers Ridge Wind Facility
Onshore wind
63.3 MWAgreement signed Grayson, VAPJM Sep 2020target 2028
Cerulean Solar and Mulberry BESS
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
62.0 MWIn study Richmond, VAPJM Feb 2020target 2031
Moon Corner Solar
Solar ยท Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
60.0 MWIn study Richmond, VAPJM Sep 2020target 2031
Mora Solar
Solar
60.0 MWAgreement signed Carbon, PAPJM Sep 2020target 2027
Carnation
Solar
58.0 MWAgreement signed Fairfield, OHPJM Sep 2020target 2028
Blossom Solar
Solar
56.0 MWAgreement signed Morrow, OHPJM Jun 2020target 2027
Bluestem Solar
Battery storage ยท RWE Solar Development, LLC
55.0 MWIn study Laporte, INPJM Sep 2020target 2023
Barrelhead
Solar ยท Barrelhead Solar, LLC
54.0 MWAgreement signed KYPJM Sep 2020target 2029
Scioty Solar
Solar
50.0 MWAgreement signed Hardin, OHPJM Sep 2020target 2027
Flatrock Creek Storage I
Battery storage
50.0 MWAgreement signed Allen, INPJM Sep 2020target 2029
Amherst Solar
Solar
50.0 MWAgreement signed Amherst, VAPJM Feb 2020target 2028
Timber Road Storage III
Battery storage
50.0 MWAgreement signed Paulding, OHPJM Mar 2020target 2029
Beckett Solar
Solar
50.0 MWAgreement signed Clarke, VAPJM Sep 2020target 2028
Top Crop Generating Facility
Battery storage ยท Blackstone Wind Farm, LLC
50.0 MWIn study Lasalle, ILPJM Mar 2020target 2023
Twin Groves Storage II
Battery storage
50.0 MWAgreement signed Mclean, ILPJM Mar 2020target 2028
Palomino Solar
Solar
50.0 MWAgreement signed Highland, OHPJM Mar 2020target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)