United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESInterconnection queue in the USA (2023 requests) — page 19
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project AI2-167, Logan County Onshore wind |
78.0 MW | In study |
| Sherbino II BESS SLF Battery storage · Phoenix Battery Storage, LLC |
77.4 MW | Agreement signed |
| Cairos Storage Solar + storage · Cairos Solar, LLC |
77.3 MW | In study |
| Dionysus Storage Solar + storage · Dionysus Solar, LLC |
77.3 MW | In study |
| Onshore wind project AI2-216, Pulaski County Onshore wind |
77.0 MW | In study |
| Myers Storage Solar + storage · BT Myers Solar, LLC |
76.0 MW | In study |
| Battery storage project AI2-040, Orange County Battery storage |
75.0 MW | In study |
| Battery storage project AI2-041, Halifax County Battery storage |
75.0 MW | In study |
| Solar project 238, Marion County Solar |
75.0 MW | In study |
| Battery storage project GI-2023-178, Imperial County Battery storage |
75.0 MW | In study |
| Solar + storage project C3-125, Millard County Solar + storage |
75.0 MW | In study |
| Battery storage project 234, Hampton County Battery storage |
75.0 MW | In study |
| Solar project 920665, Union County Solar |
75.0 MW | Agreement signed |
| Proteus Vernon Solar SLF Solar + storage · Vernon Solar and Storage LLC (a Delaware LLC) |
75.0 MW | In study |
| French Riviera Storage Battery storage · Arana Creek Battery Storage LLC |
75.0 MW | In study |
| Battery storage project GEN-2023-161, Blaine County Battery storage |
74.9 MW | In study |
| Solar project 605, Desoto County Solar · FPL |
74.9 MW | In study |
| Solar project 208, Aiken County Solar |
74.9 MW | In study |
| Solar project 326, Osceola County Solar · Duke Energy Florida, LLC |
74.9 MW | Under construction |
| Solar project 604, Desoto County Solar · FPL |
74.9 MW | In study |
| Battery storage project 230, Williamsburg County Battery storage |
74.9 MW | In study |
| Solar project 323, Jackson County Solar · Duke Energy Florida, LLC |
74.9 MW | Under construction |
| Solar project 610, Charlotte County Solar · FPL |
74.9 MW | In study |
| Solar project 607, Charlotte County Solar · FPL |
74.9 MW | In study |
| Solar project 608, Charlotte County Solar · FPL |
74.9 MW | In study |
| Solar project 612, Charlotte County Solar · FPL |
74.9 MW | In study |
| Solar project 611, Charlotte County Solar · FPL |
74.9 MW | In study |
| Solar project 609, Charlotte County Solar · FPL |
74.9 MW | In study |
| Valdivian Solar Solar · Abei Energy Green III LLC |
74.9 MW | In study |
| Solar project 338, Hamilton County Solar · Duke Energy Florida, LLC |
74.9 MW | Paused / redesign |
| Solar project 325, Osceola County Solar · Duke Energy Florida, LLC |
74.9 MW | Under construction |
| Solar project 211, Horry County Solar |
74.8 MW | In study |
| Solar project 503, Martin County Solar · FPL |
74.5 MW | In study |
| Solar project 507, Martin County Solar · FPL |
74.5 MW | In study |
| Solar project 534, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 497, Martin County Solar · FPL |
74.5 MW | In study |
| Solar project 551, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 511, Manatee County Solar · FPL |
74.5 MW | In study |
| Solar project 542, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 504, Martin County Solar · FPL |
74.5 MW | In study |
| Solar project 517, Charlotte County Solar · FPL |
74.5 MW | In study |
| Solar project 519, Charlotte County Solar · FPL |
74.5 MW | In study |
| Solar project 518, Charlotte County Solar · FPL |
74.5 MW | In study |
| Solar project 541, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 546, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 547, Hendry County Solar · FPL |
74.5 MW | In study |
| Solar project 493, Indian River County Solar · FPL |
74.5 MW | In study |
| Solar project 596, St. Lucie County Solar · FPL |
74.5 MW | In study |
| Solar project 501, Martin County Solar · FPL |
74.5 MW | In study |
| Battery storage project 222, Colleton County Battery storage |
74.5 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)309 · 110.9 GW
- ERCOT (Texas)356 · 76.0 GW
- CAISO (California)107 · 53.4 GW
- Southeast (non-ISO utilities)210 · 24.0 GW
- SPP (Southwest Power Pool)82 · 15.1 GW
- PJM (Mid-Atlantic, Midwest)156 · 14.6 GW
- MISO (Midcontinent)23 · 3,679 MW
- ISO-NE (New England)6 · 1,053 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)