United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in CAISO (California) — page 17

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 17 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Genoa Energy Storage
Battery storage
252 MWWithdrawn / abandoned Napa, CACAISO Apr 2021target 2031
Picador Energy Storage
Battery storage
252 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2021target 2032
Jaguar Energy Storage
Battery storage
252 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2034
Stony Creek Storage
Battery storage
252 MWWithdrawn / abandoned Tehama, CACAISO Apr 2021target 2031
Aratina 3
Solar + storage
251 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Rock Canyon
Solar + storage
251 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Jupiter Solar
Solar
250 MWWithdrawn / abandoned Riverside, CACAISO Apr 2014target 2018
Cantil Solar Energy
Solar
250 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2014
Randsburg Solar Energy
Solar
250 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2014
Stage Coach Solar
Solar + storage
250 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2012target 2026
Boulder Solar 3 (Fka: Boulder Solar Power C7)
Solar
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2014target 2018
Westlands Lemoore Solar
Solar
250 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2014
Big Maria Vista Solar Generating Station
Solar
250 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2012
Ward Valley Solar Energy 1
Solar
250 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2014
Colorado River Energy 2
Solar
250 MWWithdrawn / abandoned Riverside, CACAISO May 2008target 2014
Silver Leaf Solar
Solar
250 MWWithdrawn / abandoned Imperial, CACAISO Jul 2010target 2013
Arlington Valley Solar Energy II
Solar
250 MWWithdrawn / abandoned Maricopa, AZCAISO Mar 2011target 2015
Caliente Solar Energy
Solar
250 MWWithdrawn / abandoned Maricopa, AZCAISO May 2008target 2014
Mesquite Lake
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO Dec 2007target 2015
Campos Solar Energy
Solar
250 MWWithdrawn / abandoned Clark, NVCAISO May 2008target 2014
Sandy Valley Solar Project
Solar
250 MWWithdrawn / abandoned Nye, NVCAISO Apr 2012target 2018
Blue Star Wind Energy Center
Onshore wind
250 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2017
Ridgecrest Solar II (Fka Mojave Solar Peaking Power)
Solar
250 MWWithdrawn / abandoned Kern, CACAISO Aug 2007target 2013
Enn Mojave Power 1
Other
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Hyder Solar Energy Project
Solar
250 MWWithdrawn / abandoned Yuma, AZCAISO Mar 2011target 2014
Quicksilver Energy Storage
Battery storage
250 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2020target 2024
PV Coolwater-Dunn Siding
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2008target 2009
Ward Valley Solar Energy 2
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2015
Mirage Solar
Solar
250 MWWithdrawn / abandoned Kern, CACAISO Apr 2012target 2016
Quartzsite Solar Energy
Solar
250 MWWithdrawn / abandoned La Paz, AZCAISO May 2008target 2014
Rancho 2 Energy Storage
Battery storage
250 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2023
Flying Wing Solar (Fka Genesis Solar)
Solar
250 MWWithdrawn / abandoned Kern, CACAISO Nov 2006target 2015
DC Solar Energy
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2014
Montezuma Wetlands
Onshore wind
250 MWWithdrawn / abandoned Solano, CACAISO Mar 2011target 2012
Aj Solar Energy
Solar
250 MWWithdrawn / abandoned San Bernardino, CACAISO May 2008target 2014
Parker Solar Energy
Solar
250 MWWithdrawn / abandoned La Paz, AZCAISO Jun 2008target 2014
Kingsolar II
Solar
250 MWWithdrawn / abandoned Kings, CACAISO Feb 2010target 2013
Freeman Junction Solar Project
Solar
250 MWWithdrawn / abandoned Kern, CACAISO Dec 2007target 2014
Enn Mojave Power 2
Other
250 MWWithdrawn / abandoned Clark, NVCAISO Apr 2012target 2016
Bear River Energy Storage
Battery storage
250 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Verbena
Solar + storage
247 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2023
Fresno Solar 1
Solar
247 MWWithdrawn / abandoned Fresno, CACAISO Apr 2015target 2018
Fremont Valley Preservation
Solar
245 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2016
Copper Mountain Solar III (Black Hills)
Solar
242 MWWithdrawn / abandoned Clark, NVCAISO Jul 2010target 2013
Otros Alamitos Energy Storage
Battery storage
242 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2031
Patton Solar
Solar + storage
241 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Fort Mojave Solar Farms 2
Solar
240 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2011target 2013
Lassie Solar
Battery storage
240 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
Mccullough Pass Solar Project
Solar
240 MWWithdrawn / abandoned Clark, NVCAISO May 2008target 2013
Sokolata Hybrid
Solar + storage
239 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Page 17 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)