SOLAR Β· CAISO

Westlands Lemoore Solar

Westlands Lemoore Solar is a 250 MW solar request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2011 (completed)
  2. Withdrawn / abandonedMar 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
819
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates Substation 500 KV
Location
Kings County, California
Technology
Solar: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
31 March 2011
Proposed online date
December 2014
Withdrawn
March 2012

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem