United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Fresno Solar 1

Fresno Solar 1 is a 247 MW solar request withdrawn in the CAISO interconnection queue, in Fresno County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedJun 2015 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1124
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Helm-Firebaugh 230kV line
Location
Fresno County, California
Technology
Solar: 247 MW
Total requested
247 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
December 2018
Withdrawn
June 2015

Location

Marker shows the centre of Fresno County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Fresno County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem