United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESQueue requests in study in the USA (2022 requests) โ page 16
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project IC-1038, Ware County Solar |
120 MW | Paused / redesign |
| Battery storage project J2588, Jackson County Battery storage |
120 MW | In study |
| Solar + storage project AI1-074, Jackson County Solar + storage |
120 MW | In study |
| Solar project AH2-345, Lorain County Solar |
120 MW | In study |
| Battery storage project J3133, Saginaw County Battery storage |
120 MW | In study |
| Solar project J2715, Acadia Parish County Solar |
120 MW | In study |
| Solar project J3168, White County Solar |
120 MW | In study |
| Solar + storage project AI1-174, Stephenson County Solar + storage |
118 MW | In study |
| Battery storage project AH2-132, Salem County Battery storage |
117 MW | In study |
| Pioneer Hutt Solar Solar |
116 MW | Paused / redesign |
| Solar project J2350, Pulaski County Solar |
116 MW | In study |
| Solar + storage project J2382, Randolph County Solar + storage |
115 MW | In study |
| Solar + storage project J2886, Sangamon County Solar + storage |
115 MW | In study |
| Battery storage project 563648, Gaston County Battery storage |
115 MW | In study |
| Battery storage project AH2-332, Prince George's County Battery storage |
115 MW | In study |
| Solar project AH2-264, Van Wert County Solar |
115 MW | In study |
| Hayrick BESS Battery storage ยท Gransolar Texas Five LLC |
114 MW | In study |
| Solar project S0002, Carbon County Solar ยท PacifiCorp |
111 MW | In study |
| Ophelia Solar Solar ยท Ophelia Solar |
111 MW | In study |
| Solar project IC-1074, Turner County Solar |
111 MW | Paused / redesign |
| Solar project IC-1067, Treutlen County Solar |
111 MW | Paused / redesign |
| Battery storage project AI1-184, Frederick County Battery storage |
110 MW | In study |
| Solar project J2752, Montgomery County Solar |
110 MW | In study |
| Battery storage project AI1-155, Cook County Battery storage |
110 MW | In study |
| Battery storage project AI1-189, Baltimore County Battery storage |
110 MW | In study |
| Battery storage project J2551, Putnam County Battery storage |
110 MW | In study |
| Inertia BESS 3 Battery storage |
108 MW | Paused / redesign |
| Battery storage project AH2-375, Stephenson County Battery storage |
106 MW | In study |
| Solar project J2639, Bradley County Solar |
106 MW | In study |
| Solar project J2634, Ouachita County Solar |
106 MW | In study |
| Burgos Solar Solar ยท Twin Oaks Solar, LLC |
106 MW | In study |
| Reis Solar Solar ยท Greenalia Solar Power Reis LLC |
106 MW | In study |
| Solar project J2693, Franklin Parish County Solar |
105 MW | In study |
| Solar project AI1-021, Pittsylvania County Solar |
105 MW | In study |
| Battery storage project AH2-131, Gloucester County Battery storage |
104 MW | In study |
| Bronze Quinta Storage Battery storage ยท KCE TX 28, LLC |
104 MW | In study |
| Appaloosa Run BESS Battery storage ยท APPALOOSA RUN STORAGE, LLC |
103 MW | In study |
| Onshore wind project AI1-006, Randolph County Onshore wind |
103 MW | In study |
| Two Rivers Solar Solar + storage |
102 MW | In study |
| Half Moon 2 BESS Battery storage |
102 MW | Paused / redesign |
| Kennedy Solar Solar + storage ยท Kennedy Bypass Solar LLC |
102 MW | In study |
| Triangle Ranch Delta Onshore wind |
102 MW | Paused / redesign |
| Rose Quartz BESS Battery storage ยท Rose Quartz BESS, LLC |
101 MW | In study |
| Blanket Ranch South Solar Solar + storage ยท Blanket Ranch South Solar, LLC |
101 MW | In study |
| Saltillo Storage Battery storage |
101 MW | Paused / redesign |
| Luthor Solar Solar ยท TREX US Luthor LLC |
101 MW | In study |
| Glory Bee Storage Solar + storage ยท Riley Solar LLC |
101 MW | In study |
| Pinewood BESS Battery storage |
101 MW | Paused / redesign |
| Venus Mill Storage Battery storage |
101 MW | Paused / redesign |
| Padrino BESS Battery storage |
101 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)251 ยท 87.7 GW
- MISO (Midcontinent)426 ยท 80.7 GW
- PJM (Mid-Atlantic, Midwest)301 ยท 37.9 GW
- ERCOT (Texas)172 ยท 33.5 GW
- Southeast (non-ISO utilities)98 ยท 11.2 GW
- SPP (Southwest Power Pool)21 ยท 3,927 MW
- ISO-NE (New England)2 ยท 325 MW
- NYISO (New York)1 ยท 20.0 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)