United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2018 requests) โ€” page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests ยท page 14 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project 75, Colleton County
Solar
100 MWWithdrawn / abandoned Colleton, SCSoutheast Jan 2018target 2019
Solar project 96, Kershaw County
Solar
100 MWWithdrawn / abandoned Kershaw, SCSoutheast Apr 2018target 2020
Solar project AD2-169, Greensville County
Solar
100 MWWithdrawn / abandoned Greensville, VAPJM Mar 2018target 2020
Solar project IC-683, Jones County
Solar
100 MWWithdrawn / abandoned Jones, MSSoutheast Mar 2018
Blue Star Solar
Solar ยท Granada Solar, LLC (Conti)
100 MWWithdrawn / abandoned Washington, NYNYISO Aug 2018
Battery storage project GEN-2018-095, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, MOSPP Nov 2018target 2023
Solar + storage project 1056, Juab County
Solar + storage
100 MWWithdrawn / abandoned Juab, UTWest Aug 2018target 2021
Solar + storage project 1052, Utah County
Solar + storage
100 MWWithdrawn / abandoned Utah, UTWest Jul 2018target 2021
Solar project 339, Colbert County
Solar
100 MWWithdrawn / abandoned Colbert, ALSoutheast Feb 2018
Solar project 113, Orangeburg County
Solar
100 MWWithdrawn / abandoned Orangeburg, SCSoutheast Jul 2018target 2020
Solar project AD2-156, Erie County
Solar
100 MWWithdrawn / abandoned Erie, OHPJM Mar 2018target 2020
Robles Storage
Other ยท Cypress Creek Renewables
100 MWWithdrawn / abandoned Dimmit, TXERCOT Jul 2018target 2020
Solar project J1052, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, MIMISO Mar 2018target 2020
Solar + storage project Q286, Yavapai County
Solar + storage
100 MWWithdrawn / abandoned Yavapai, AZWest Sep 2018target 2021
Other project AE1-077, Allegany County
Other
100 MWWithdrawn / abandoned Allegany, MDPJM Aug 2018target 2020
Solar project AE1-137, Randolph County
Solar
100 MWWithdrawn / abandoned Randolph, INPJM Sep 2018target 2021
Solar project J995, Brown County
Solar
100 MWWithdrawn / abandoned Brown, ILMISO Mar 2018target 2021
Onshore wind project GEN-2018-053, Jasper County
Onshore wind
100 MWWithdrawn / abandoned Jasper, MOSPP May 20182025
Owen Solar
Solar ยท Belltown Power
100 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
Huckleberry Ridge Energy
Battery storage ยท Energy Storage Resources, LLC
100 MWWithdrawn / abandoned Orange, NYNYISO Jul 2018
Solar project J969, Tuscola County
Solar
100 MWWithdrawn / abandoned Tuscola, MIMISO Mar 2018target 2020
Shellman Solar
Solar
100 MWWithdrawn / abandoned Randolph, GASoutheast Jul 2018target 2022
Solar project IC-734, Grady County
Solar
100 MWWithdrawn / abandoned Grady, GASoutheast Sep 2018
Solar project AD2-176, Mchenry County
Solar
100 MWWithdrawn / abandoned Mchenry, ILPJM Mar 2018target 2021
Solar project AD2-208, City Of Portsmouth County
Solar
100 MWWithdrawn / abandoned City Of Portsmouth, VAPJM Mar 2018
Solar project AE1-220, Nelson County
Solar
100 MWWithdrawn / abandoned Nelson, VAPJM Sep 2018target 2022
Solar project J987, Montgomery County
Solar
100 MWWithdrawn / abandoned Montgomery, MOMISO Mar 2018target 2023
Solar project 5224, Sumter County
Solar ยท Duke Energy Renewables Solar LLC
100 MWWithdrawn / abandoned Sumter, SCSoutheast Oct 2018
Solar + storage project AE1-248, Southampton County
Solar + storage
100 MWWithdrawn / abandoned Southampton, VAPJM Aug 2018target 2021
Solar + storage project Company JB, Churchill County
Solar + storage
100 MWWithdrawn / abandoned Churchill, NVWest Sep 2018target 2021
Battery storage project GEN-2018-104, Jackson County
Battery storage
100 MWWithdrawn / abandoned Jackson, MOSPP Nov 2018target 2023
Battery storage project Company IZ, Carson City County
Battery storage
100 MWWithdrawn / abandoned Carson City, NVWest Sep 2018target 2028
Onshore wind project GEN-2018-040, Ralls County
Onshore wind
100 MWWithdrawn / abandoned Ralls, MOSPP May 20182025
Battery storage project Company 160, Clark County
Battery storage
100 MWWithdrawn / abandoned Clark, NVWest Mar 2018target 2021
Solar project J1070, Washington County
Solar
100 MWWithdrawn / abandoned Washington, MSMISO Mar 2018target 2021
Solar project J1134, White County
Solar
100 MWWithdrawn / abandoned White, ARMISO Mar 2018target 2021
Solar project J1157, Hinds County
Solar
100 MWWithdrawn / abandoned Hinds, MSMISO Mar 2018target 2020
Solar project AE1-031, Montgomery County
Solar
100 MWWithdrawn / abandoned Montgomery, OHPJM Jun 2018target 2020
Battery storage project J1104, Washington County
Battery storage
100 MWWithdrawn / abandoned Washington, WIMISO Mar 2018target 2021
Battery storage project Q52, Maricopa County
Battery storage
100 MWWithdrawn / abandoned Maricopa, AZWest Dec 2018target 2023
Battery storage project AE1-002, Benton County
Battery storage
100 MWWithdrawn / abandoned Benton, INPJM Apr 2018target 2020
Solar project GEN-2018-097, Parmer County
Solar
100 MWWithdrawn / abandoned Parmer, TXSPP Nov 2018target 2027
Solar project AD2-207, Isle Of Wight County
Solar
100 MWWithdrawn / abandoned Isle Of Wight, VAPJM Mar 2018target 2020
Solar project GEN-2018-020, Curry County
Solar
100 MWWithdrawn / abandoned Curry, NMSPP May 2018target 2020
Solar project J1137, Jackson County
Solar
100 MWWithdrawn / abandoned Jackson, ARMISO Mar 2018target 2021
Solar project J1159, Walker County
Solar
100 MWWithdrawn / abandoned Walker, TXMISO Mar 2018target 2020
Solar project 114, Williamsburg County
Solar
100 MWWithdrawn / abandoned Williamsburg, SCSoutheast Jul 2018target 2020
Mcgrath Energy Center 1
Battery storage
100 MWWithdrawn / abandoned Ventura, CACAISO Apr 2018target 2020
Solar + storage project 61, Pima County
Solar + storage
100 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2020
Solar project J1110, Mower County
Solar
100 MWWithdrawn / abandoned Mower, MNMISO Mar 2018target 2021

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)