United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
SOLAR Β· SOUTHEASTSolar project IC-683, Jones County
Solar project IC-683, Jones County is a 100 MW solar request withdrawn in the Southeast interconnection queue, in Jones County, Mississippi, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedJul 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-683
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Laurel East - Waynesboro 115 kV Line
- Location
- Jones County, Mississippi
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 20 March 2018
- Withdrawn
- July 2018
Location
Marker shows the centre of Jones County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Jones County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem