OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in MISO (Midcontinent) — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown3,261621.9 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

3,261 requests · page 14 of 66
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2600, Wabasha County
Solar
245 MWWithdrawn / abandoned Wabasha, MNMISO Sep 2022target 2026
Solar project J824, Sullivan County
Solar
245 MWWithdrawn / abandoned Sullivan, INMISO Jun 2017target 2020
Gas project J413, Marquette County
Gas
243 MWWithdrawn / abandoned Marquette, MIMISO Nov 2014target 2017
Onshore wind project G764, Minnehaha County
Onshore wind
242 MWWithdrawn / abandoned Minnehaha, SDMISO Mar 2007target 2013
Gas project J3831, Madison County
Gas
240 MWWithdrawn / abandoned Madison, INMISO Oct 2024target 2029
Gas project G765, Brookings County
Gas
240 MWWithdrawn / abandoned Brookings, SDMISO Feb 2011target 2010
Solar + storage project J2617, Van Buren County
Solar + storage
240 MWWithdrawn / abandoned Van Buren, MIMISO Sep 2022target 2026
Onshore wind project J3956, Wilkin County
Onshore wind
240 MWWithdrawn / abandoned Wilkin, MNMISO Apr 2025target 2030
Solar + storage project J2923, Columbia County
Solar + storage
240 MWWithdrawn / abandoned Columbia, ARMISO Sep 2022target 2028
Battery storage project J2585, Greene County
Battery storage
240 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2025
Onshore wind project J3751, Madison County
Onshore wind
236 MWWithdrawn / abandoned Madison, ILMISO Apr 2024target 2028
Solar + storage project J2650, Hancock County
Solar + storage
236 MWWithdrawn / abandoned Hancock, INMISO Sep 2022target 2027
Onshore wind project J3766, Pottawattamie County
Onshore wind
235 MWWithdrawn / abandoned Pottawattamie, IAMISO Apr 2024target 2026
Gas project J444, Wayne County
Gas
235 MWWithdrawn / abandoned Wayne, MIMISO May 2015target 2017
Solar project J2695, Carroll County
Solar
234 MWWithdrawn / abandoned Carroll, INMISO Sep 2022target 2027
Gas project J271, Montcalm County
Gas
232 MWWithdrawn / abandoned Montcalm, MIMISO Mar 2013
Gas project J359, Woodbury County
Gas
232 MWWithdrawn / abandoned Woodbury, IAMISO May 2014target 2015
Gas project J366, Pottawattamie County
Gas
232 MWWithdrawn / abandoned Pottawattamie, IAMISO May 2014target 2016
Gas project J356, Polk County
Gas
232 MWWithdrawn / abandoned Polk, IAMISO May 2014
Solar project J3595, Sunflower County
Solar
230 MWWithdrawn / abandoned Sunflower, MSMISO Apr 2024target 2028
Solar project J3337, Stoddard County
Solar
230 MWWithdrawn / abandoned Stoddard, MOMISO Apr 2024target 2028
Gas project G033, Monroe County
Gas
230 MWWithdrawn / abandoned Monroe, IAMISO Mar 2000target 2001
Solar project J3271, Mississippi County
Solar
230 MWWithdrawn / abandoned Mississippi, ARMISO Apr 2024target 2028
Solar project J2709, Miami County
Solar
228 MWWithdrawn / abandoned Miami, INMISO Sep 2022target 2027
Onshore wind project J2363, Washington County
Onshore wind
226 MWWithdrawn / abandoned Washington, IAMISO Sep 2022target 2030
Solar project J2348, Webster Parish County
Solar
225 MWWithdrawn / abandoned Webster Parish, LAMISO Sep 2022target 2026
Other project G120, Itasca County
Other
225 MWWithdrawn / abandoned Itasca, MNMISO Aug 2001
Solar + storage project J2076, San Jacinto County
Solar + storage
225 MWWithdrawn / abandoned San Jacinto, TXMISO Aug 2021target 2024
Onshore wind project J593, Williams County
Onshore wind
224 MWWithdrawn / abandoned Williams, NDMISO May 2016target 2018
Onshore wind project J2915, Clark County
Onshore wind
223 MWWithdrawn / abandoned Clark, MOMISO Sep 2022target 2028
Onshore wind project J3335, Mclean County
Onshore wind
222 MWWithdrawn / abandoned Mclean, ILMISO Apr 2024target 2028
Gas project J280, Goodhue County
Gas
221 MWWithdrawn / abandoned Goodhue, MNMISO Mar 2013
Solar project J3173, Jackson County
Solar
220 MWWithdrawn / abandoned Jackson, ARMISO Sep 2022target 2026
Onshore wind project J2964, Tallahatchie County
Onshore wind
220 MWWithdrawn / abandoned Tallahatchie, MSMISO Sep 2022target 2025
Solar project J3752, Aitkin County
Solar
220 MWWithdrawn / abandoned Aitkin, MNMISO Apr 2024target 2028
Solar project J2513, Vigo County
Solar
220 MWWithdrawn / abandoned Vigo, INMISO Sep 2022target 2025
Battery storage project J3647, Gratiot County
Battery storage
220 MWWithdrawn / abandoned Gratiot, MIMISO Apr 2024target 2028
Solar project J2705, Assumption Parish County
Solar
220 MWWithdrawn / abandoned Assumption Parish, LAMISO Sep 2022target 2027
Other project G055, Dubuque County
Other
220 MWWithdrawn / abandoned Dubuque, IAMISO Aug 2000target 2007
Gas project J863, Dakota County
Gas
220 MWWithdrawn / abandoned Dakota, MNMISO Jun 2017target 2021
Solar project J3951, Polk County
Solar
218 MWWithdrawn / abandoned Polk, MNMISO Feb 2025target 2030
Solar + storage project J3115, Sharkey County
Solar + storage
216 MWWithdrawn / abandoned Sharkey, MSMISO Sep 2022target 2026
Battery storage project J3584, Lee County
Battery storage
215 MWWithdrawn / abandoned Lee, ARMISO Apr 2024target 2028
Solar project J3520, Champaign County
Solar
215 MWWithdrawn / abandoned Champaign, ILMISO Apr 2024target 2028
Solar project J3893, Phillips County
Solar
214 MWWithdrawn / abandoned Phillips, ARMISO Feb 2025target 2030
Battery storage project J2095, Tama County
Battery storage
212 MWWithdrawn / abandoned Tama, IAMISO Aug 2021target 2024
Onshore wind project J742, Cottonwood County
Onshore wind
211 MWWithdrawn / abandoned Cottonwood, MNMISO Nov 2016target 2020
Onshore wind project G561, Bureau County
Onshore wind
210 MWWithdrawn / abandoned Bureau, ILMISO Oct 2005target 2007
Solar project J1737, Rush County
Solar
210 MWWithdrawn / abandoned Rush, INMISO Oct 2021target 2023
Battery storage project J2535, Vermilion Parish County
Battery storage
210 MWWithdrawn / abandoned Vermilion Parish, LAMISO Sep 2022target 2026
Page 14 of 66

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)