Gas project J863, Dakota County

Gas project J863, Dakota County is a 220 MW gas request withdrawn in the MISO interconnection queue, in Dakota County, Minnesota, connecting to NORTHERN STATES POWER COMPANY.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedDec 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J863
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN STATES POWER COMPANY
Connection point (POI)
Rosemount - Nininger 115kV Line
Location
Dakota County, Minnesota
Technology
Gas: 220 MW
Total requested
220 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
January 2021
Withdrawn
December 2018

Location

Marker shows the centre of Dakota County; the queue data does not give exact sites.