Withdrawn queue requests in the USA (2018 requests) — page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,424226.5 GW
Active in queue67.1 GW348 requests
Agreement signed32.4 GW175 requests
Withdrawn1,424226.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,424 requests · page 11 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1108, Douglas County
Solar
150 MWWithdrawn / abandoned Douglas, MNMISO Mar 2018target 2021
Solar project AD2-063, Charlotte County
Solar
150 MWWithdrawn / abandoned Charlotte, VAPJM Feb 2018target 2021
Thickgrass Solar
Solar · Origis Energy
149 MWWithdrawn / abandoned Matagorda, TXERCOT Jul 2018target 2021
Onshore wind project J1120, Jefferson County
Onshore wind
145 MWWithdrawn / abandoned Jefferson, TXMISO Mar 2018target 2021
Onshore wind project J1176, Cerro Gordo County
Onshore wind
145 MWWithdrawn / abandoned Cerro Gordo, IAMISO Mar 2018target 2021
Gas project AD2-104, Baltimore County
Gas
145 MWWithdrawn / abandoned Baltimore, MDPJM Mar 2018target 2019
French Goldston Solar
Solar · Belltown Power
144 MWWithdrawn / abandoned Young, TXERCOT Jan 2018target 2023
Battery Storage
Battery storage
143 MWWithdrawn / abandoned Barnstable, MAISO-NE Mar 2018target 2021
Solar project J972, St. Francis County
Solar
140 MWWithdrawn / abandoned St. Francis, ARMISO Mar 2018target 2021
Gold Creek Solar
Solar · S Power
140 MWWithdrawn / abandoned Dawson, TXERCOT May 2018target 2021
Solar project AE1-228, Lee County
Solar
140 MWWithdrawn / abandoned Lee, ILPJM Sep 2018target 2021
Gas project AE1-070, Will County
Gas · Elwood Energy, LLC
135 MWWithdrawn / abandoned Will, ILPJM Jul 2018target 2020
Gas project AD2-198, Will County
Gas
135 MWWithdrawn / abandoned Will, ILPJM Mar 2018target 2020
Solar + storage project AE1-055, Hudson County
Solar + storage
134 MWWithdrawn / abandoned Hudson, NJPJM Jul 2018target 2021
Solar project IC-692, Decatur County
Solar
130 MWWithdrawn / abandoned Decatur, GASoutheast Apr 2018
Solar project J1036, Cottonwood County
Solar
130 MWWithdrawn / abandoned Cottonwood, MNMISO Mar 2018target 2020
Solar project GEN-2018-088, Bowie County
Solar
130 MWWithdrawn / abandoned Bowie, TXSPP Nov 2018target 2027
Monte Bueno
Onshore wind · Terra-Gen
129 MWWithdrawn / abandoned Hidalgo, TXERCOT Apr 2018target 2022
Havana Wind
Onshore wind · Terra-Gen
129 MWWithdrawn / abandoned Hidalgo, TXERCOT Apr 2018target 2022
Ravenswood Energy Storage 2
Battery storage · Helix Ravenswood, LLC
129 MWWithdrawn / abandoned Queens, NYNYISO Mar 2018
Ravenswood Energy Storage 1
Battery storage · Helix Ravenswood, LLC
129 MWWithdrawn / abandoned Queens, NYNYISO Mar 2018
Gas project 338, Sweet Grass County
Gas
128 MWWithdrawn / abandoned Sweet Grass, MTWest Jan 2018target 2019
Philosun
Solar · Alpin Sun
127 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
El Zorro Storage
Other · Cypress Creek Renewables
127 MWWithdrawn / abandoned Webb, TXERCOT Jun 2018target 2021
Atascosa I Solar
Solar · Core Solar
127 MWWithdrawn / abandoned Dawson, TXERCOT Jun 2018target 2022
Century Oak Wind
Onshore wind · Engie
126 MWWithdrawn / abandoned Callahan, TXERCOT Jan 2018target 2023
Solar project GEN-2018-023, Little River County
Solar
126 MWWithdrawn / abandoned Little River, ARSPP Apr 2018target 2021
Highwire Storage
Battery storage · Cypress Creek Renewables
126 MWWithdrawn / abandoned ERCOT Mar 2018target 2020
Onshore wind project J1017, Carroll County
Onshore wind
125 MWWithdrawn / abandoned Carroll, INMISO Mar 2018target 2021
Bull Run Solar Energy Center
Solar · Invenergy Solar Development North America LLC
125 MWWithdrawn / abandoned Clinton, NYNYISO Jan 2018
Solar project IC-688, Perry County
Solar
125 MWWithdrawn / abandoned Perry, MSSoutheast Mar 2018
Battery storage project GEN-2018-090, Washington County
Battery storage
125 MWWithdrawn / abandoned Washington, NESPP Nov 2018target 2027
Solar + storage project 60, Pima County
Solar + storage
125 MWWithdrawn / abandoned Pima, AZWest Sep 2018target 2020
Solar project J1057, Jackson County
Solar
125 MWWithdrawn / abandoned Jackson, MNMISO Mar 2018target 2021
Solar project AD2-188, Lee County
Solar
125 MWWithdrawn / abandoned Lee, ILPJM Mar 2018target 2021
Magnet Wind
Onshore wind · Lane City Wind, LLC
125 MWWithdrawn / abandoned Wharton, TXERCOT Apr 2018target 2021
Solar project IC-728, Ware County
Solar
124 MWWithdrawn / abandoned Ware, GASoutheast Aug 2018
Onshore wind project TCS-02, Adams County
Onshore wind
123 MWWithdrawn / abandoned Adams, WAWest Jun 2018target 2021
Onshore wind project 62, Adams County
Onshore wind
123 MWWithdrawn / abandoned Adams, WAWest Jun 2018target 2021
Onshore wind project GEN-2018-130, Knox County
Onshore wind
122 MWWithdrawn / abandoned Knox, NESPP Nov 2018target 2020
Solar project J1086, Nobles County
Solar
120 MWWithdrawn / abandoned Nobles, MNMISO Mar 2018target 2021
Solar project LGE-GIS-2018-002, Daviess County
Solar
120 MWWithdrawn / abandoned Daviess, KYSoutheast Oct 2018target 2022
Highline Solar Energy Center
Solar + storage
120 MWWithdrawn / abandoned Kern, CACAISO Apr 2018target 2021
EK Tipton Solar
Solar · EnergieKontor US Texas SP 1 LLC
120 MWWithdrawn / abandoned Reeves, TXERCOT Sep 2018target 2023
Solar project IC-765, Terrell County
Solar
120 MWWithdrawn / abandoned Terrell, GASoutheast Dec 2018
Cadence Solar II Energy Center
Solar
120 MWWithdrawn / abandoned Union, OHPJM Mar 2018target 2026
Solar project LGE-GIS-2018-006, Hopkins County
Solar
120 MWWithdrawn / abandoned Hopkins, KYSoutheast Oct 2018target 2022
Solar + storage project AE1-251, Scott County
Solar + storage
120 MWWithdrawn / abandoned Scott, KYPJM Sep 2018target 2021
Solar project GEN-2018-054, Linn County
Solar
120 MWWithdrawn / abandoned Linn, KSSPP May 2018target 2026
Blackbird Solar
Solar
120 MWWithdrawn / abandoned Pulaski, VAPJM Mar 2018target 2021
Page 11 of 29

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)