United States βΊ Grid βΊ Interconnection queues βΊ Kentucky
SOLAR Β· SOUTHEASTSolar project LGE-GIS-2018-006, Hopkins County
Solar project LGE-GIS-2018-006, Hopkins County is a 120 MW solar request withdrawn in the Southeast interconnection queue, in Hopkins County, Kentucky, connecting to Louisville Gas & Electric and Kentucky Utilities Energy.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2018 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- LGE-GIS-2018-006
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Louisville Gas & Electric and Kentucky Utilities Energy
- Connection point (POI)
- North Earlington - River Quenn Tap 161 kV line
- Location
- Hopkins County, Kentucky
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Service type
- NRIS and ERIS
- Queue status
- Withdrawn
- Entered queue
- 1 October 2018
- Proposed online date
- June 2022
Location
Marker shows the centre of Hopkins County; the queue data does not give exact sites.
Other requests in Hopkins County
- Gas project LGE-GIS-2024-002, Hopkins CountyGas Β· 75.0 MW Β· agreement signed
- Solar project LGE-GIS-2023-007, Hopkins CountySolar Β· 138 MW Β· in study
- Solar project 452, Hopkings CountySolar Β· 200 MW Β· withdrawn
- Solar project LGE-GIS-2019-020, Hopkins CountySolar Β· 85.0 MW Β· withdrawn
- Solar project J2146, Hopkins CountySolar Β· 45.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem