Projects with signed interconnection agreements in the USA — page 10

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 10 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Drake BESS
Battery storage · Mallard Energy Storage LLC
257 MWAgreement signed Collin, TXERCOT Jun 2022target 2026
Captiva Energy Storage
Battery storage
257 MWAgreement signed Orange, CACAISO Apr 2020target 2028
Shepard Energy Storage
Battery storage · Shepard Energy Storage LLC
257 MWAgreement signed Galveston, TXERCOT Dec 2022target 2027
Alila Solar
Solar + storage · Electra Energy Project, LLC
257 MWAgreement signed San Patricio, TXERCOT Oct 2020target 2028
Hastings Park BESS
Battery storage · Brazos Roots BESS, LLC
256 MWAgreement signed Brazoria, TXERCOT Aug 2024target 2027
Commerce Energy Storage 3
Battery storage
256 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2031
Delamar Energy Storage
Battery storage
256 MWAgreement signed Clark, NVCAISO Apr 2020target 2027
SanPat Solar II
Solar · CGRP 04, LLC
256 MWAgreement signed San Patricio, TXERCOT Feb 2022target 2027
Tulsita Solar
Solar · Ray Ranch Solar LLC
256 MWAgreement signed Goliad, TXERCOT Dec 2018target 2026
Zeya BESS
Battery storage · BRP Zeya BESS LLC
255 MWAgreement signed Galveston, TXERCOT May 2021target 2026
Onshore wind project GEN-2018-067, Williams County
Onshore wind
255 MWAgreement signed Williams, NDSPP Oct 2018target 2028
Solar project CLPT G18, Converse County
Solar · DUTC bn, LLC
255 MWAgreement signed Converse, WYWest Jun 2022target 2024
Ciervo Mountain Hybrid
Solar + storage
255 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Maleza Solar
Solar + storage · Brush Solar LLC
255 MWAgreement signed Wharton, TXERCOT Dec 2018target 2027
Sandrift Storage 1
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2030
Sandrift Storage 2
Battery storage
255 MWAgreement signed Riverside, CACAISO Apr 2021target 2031
Roseland Solar
Solar · Enel Green Power Roseland Solar, LLC
254 MWAgreement signed Falls, TXERCOT Nov 2018target 2025
Roseland Solar II
Solar · Enel Green Power Roseland Solar, LLC
254 MWAgreement signed Falls, TXERCOT Oct 2021target 2025
North Rosamond Solar
Solar + storage
253 MWAgreement signed Kern, CACAISO Jul 20102019
Cibeles Solar
Solar · Elawan Cibeles Solar, LLC
252 MWAgreement signed Mclennan, TXERCOT May 2022target 2027
Onshore wind project GEN-2019-030, Ford County
Onshore wind
252 MWAgreement signed Ford, KSSPP Apr 2019target 2027
Greenwood Energy Storage
Battery storage
252 MWAgreement signed Los Angeles, CACAISO Apr 2021target 2032
Zorin Storage
Battery storage
252 MWAgreement signed Alameda, CACAISO Apr 2021target 2034
LH252W
Onshore wind
252 MWAgreement signed Grant, NMWest Mar 2023target 2027
Onshore wind project 2019-G2
Onshore wind
252 MWAgreement signed West Nov 2018target 2022
Solar project GEN-2018-055, Grady County
Solar
252 MWAgreement signed Grady, OKSPP May 2018target 2026
Buzios Solar
Solar + storage · Roaring Springs Solar, LLC
252 MWAgreement signed Motley, TXERCOT Sep 2022target 2026
Onshore wind project 2019-G1
Onshore wind
252 MWAgreement signed West Nov 2018target 2021
Solar project GEN-2018-015, Cottle County
Solar
252 MWAgreement signed Cottle, TXSPP Apr 2018target 2027
Eval Storage
Battery storage · Hecate Grid East Valley Storage LLC
252 MWAgreement signed Cameron, TXERCOT Oct 2020target 2028
Clairemont Solar 1
Solar · Clairemont Solar LLC
252 MWAgreement signed Kent, TXERCOT Jan 2025target 2029
Buffalo Creek BESS
Battery storage · Old 300 Storage Center, LLC
251 MWAgreement signed Fort Bend, TXERCOT Mar 2024target 2026
Sugaree Solar
Solar · Sugaree Solar LLC
251 MWAgreement signed Maverick, TXERCOT Oct 2024target 2028
Althea Storage
Battery storage · Sugaree Solar LLC
251 MWAgreement signed Maverick, TXERCOT Feb 2025target 2028
Clutch City Solar Phase II
Solar · HZ SOLAR I, LLC
251 MWAgreement signed Brazoria, TXERCOT Feb 2023target 2028
Rock Creek BESS
Battery storage · Flat Rock Energy Center, LLC
251 MWAgreement signed Kendall, TXERCOT Feb 2024target 2028
Tanglewood Solar
Solar · Brazoria Solar, LLC
251 MWAgreement signed Brazoria, TXERCOT Jul 2020target 2026
Adamstown Solar
Solar · Adams Creek Solar Project, LLC
251 MWAgreement signed Wichita, TXERCOT Nov 2018target 2027
Tiger Solar
Solar · Vaca Del Sol, LLC
251 MWAgreement signed Jones, TXERCOT Apr 2021target 2027
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Solar + storage project GEN-2020-008, Stevens County
Solar + storage
250 MWAgreement signed Stevens, KSSPP Apr 2020target 2028
Coal project BHBE G1, Campbell County
Coal · Basin Electric
250 MWAgreement signed Campbell, SDWest Feb 2001target 2011
Solar + storage project GI-2018-24, Pueblo County
Solar + storage
250 MWAgreement signed Pueblo, COWest Aug 20182022
Solar project Company NR, Lassen County
Solar
250 MWAgreement signed Lassen, CAWest Sep 2022target 2030
Battery storage project Company 237, Clark County
Battery storage
250 MWAgreement signed Clark, NVWest Jan 2023target 2026
Commerce Energy Storage
Battery storage
250 MWAgreement signed Los Angeles, CACAISO Apr 2019target 2026
Samson Solar 3
Solar · Samson Solar Energy III LLC
250 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Battery storage project GEN-2021-043, Lancaster County
Battery storage
250 MWAgreement signed Lancaster, NESPP Apr 2021target 2030
Solar project J1216, Washington County
Solar
250 MWAgreement signed Washington, ILMISO Apr 2019target 2026
Solar project IC-950, Mcduffie County
Solar
250 MWAgreement signed Mcduffie, GASoutheast Apr 2021target 2024
Page 10 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)